Did you know that under JBCC Edition 6.2 (May 2018), clause 11.1 requires the Contractor to provide the Employer with a construction guarantee within 15 days of acceptance of the tender? Failure to do so entitles the Employer to either terminate the agreement or withhold interim payment certificates until they total 10% of the required contract sum.