A cost-plus contract pays the contractor's costs plus a fee and has no built-in ceiling. Overruns and rework are costs, and the fee is charged on them. A Guaranteed Maximum Price, a not-to-exceed clause and an audit right are what put a number in it. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Contract terms: cost-plus, guaranteed maximum price, audit rights www.wclfirm.com/how-to-pay-contractor-florida-without-paying-twice/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/18/2026

A draw schedule tied to dates pays the contractor on the calendar; one tied to milestones pays for work that exists. Money paid ahead of the work is the contractor's working capital rather than the owner's leverage, and if the contractor abandons the job it is recoverable only by suit. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. s. 713.06(3) - proper payments; contract terms govern draws www.wclfirm.com/how-to-pay-contractor-florida-without-paying-twice/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/18/2026

The deadlines in Florida's Construction Lien Law - the Notice to Owner, the Claim of Lien, the year to enforce it, the life of the Notice of Commencement - run on the statute's calendar, not the job's. A contractual time extension for weather does not extend them. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. ch. 713 - statutory deadlines are not tolled by a work stoppage www.wclfirm.com/what-is-a-notice-of-commencement-florida/ www.wclfirm.com/how-long-does-a-construction-lien-last-florida/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/17/2026

An action founded on the design, planning or construction of an improvement must be brought within 4 years of the earliest of the temporary certificate of occupancy, certificate of occupancy, certificate of completion, or abandonment; a latent defect runs from discovery. In every case the action is barred 7 years after that same date. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. s. 95.11(3) - 4-year limitation and 7-year repose for construction Fla. Stat. ch. 558 - pre-suit notice of a construction defect Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/17/2026

When a contractor abandons a job, the owner's remedy runs through the contract. A contract with no start date, no completion date, no definition of abandonment and no termination-for-cause clause leaves the owner little to enforce, and a deposit is recoverable only against a contractor who still has assets. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Contract terms govern abandonment and deposit recovery www.wclfirm.com/how-to-pay-contractor-florida-without-paying-twice/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/16/2026

A Notice to Owner mailed within 40 days of first furnishing is effective on mailing. Mailed after the 40th day, it is effective only on delivery, and the 45-day deadline then depends on when it actually arrives. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. s. 713.06(2)(a) - Notice to Owner; timing of service Fla. Stat. s. 713.18 - manner of serving notices www.wclfirm.com/how-long-is-a-notice-to-owner-good-for-florida/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/16/2026

The 90 days to record a Claim of Lien run from the last day of actual furnishing. Punch-list work is a fact-dependent grey zone that may not qualify as final furnishing. Be conservative and record earlier rather than later. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. s. 713.08 - claim of lien; 90 days from final furnishing www.wclfirm.com/how-long-does-a-construction-lien-last-florida/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/15/2026

The Notice of Commencement is the owner's document and goes out to the public record. The Notice to Owner is the subcontractor's or supplier's and goes to the owner, generally within 45 days of first furnishing. A recorded Notice of Commencement does not preserve anyone's lien rights; the Notice to Owner does. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. s. 713.06(2) - Notice to Owner www.wclfirm.com/what-is-a-notice-of-commencement-florida/ www.wclfirm.com/how-long-is-a-notice-to-owner-good-for-florida/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/15/2026

On most permitted jobs above the statutory threshold, the building department will not release the permit for inspection until a recorded copy of the Notice of Commencement is filed with it. That is the practical enforcement mechanism. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. s. 713.135 - permit issuance and the Notice of Commencement www.wclfirm.com/what-is-a-notice-of-commencement-florida/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

09/14/2026

A Notice of Commencement must be signed by the owner and notarized, recorded in the county's official records, and a certified copy posted at the job site. All three. A notice that was recorded but never posted, or filled out and never recorded, does not do the work it exists to do. Call a Construction Lawyer Board Certified by The Florida Bar: (407) 926-4100 Williams Law Firm | Orlando, Florida Glenn Williams, Esq., Board Certified in Construction Law by The Florida Bar Sources: Fla. Stat. s. 713.13 - Notice of Commencement; recording and posting www.wclfirm.com/what-is-a-notice-of-commencement-florida/ Not legal advice. Licensed in Florida only, laws differ where you live. No attorney-client relationship is created without a Fully Signed Legal Representation Agreement.

Address

950 S Winter Park Boulevard , Suite 250
Casselberry, FL
32707

Telephone

+14079264100

Website

Alerts

Be the first to know and let us send you an email when My Construction Attorney posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share

Category