PAUNAWA
Ano: NGCP at PELCO II Scheduled Power Interruption
Kailan: Enero 3, 2025 (Biyernes)
Oras: Pagitan ng 6:00 ng umaga hanggang 6:00 ng hapon (mga 12 na oras)
Mga Apektadong Lugar:
MABALACAT - Lahat ng Barangay
MAGALANG - Brgy. Sta. Lucia Barrio at Sta. Lucia Resettlement (Phase 1 at 2)
Dahilan:
NGCP
• Electrical testing of new 69kV power circuit breaker, disconnect switches and earthing switch;
• Commissioning and energization of new 69kV power circuit breaker, disconnect switches and earthing switch at Mexico Substation;
• Testing of feeder protection relays;
• SCADA control integrity test & alarm status validation test for the new power circuit breaker; and
• TL maintenance along the line.
PELCO II
• Payout of 795MCM ACSR segment of 69kV line in front of Mabiga Substation;
• Payout of 795MCM ACSR segment of 67kV line in front of Sta. Maria Substation;
• Resetting of primary protection of 10 MVA mobile substation;
• Replacement of 69k disconnect switch at Mabiga Substation;
• Substation works;
• Metering works;
• O & M works; and
• Clearing of lines
Para sa kaalaman ng lahat.