04/04/2024
āĻāĻāĻāύ āĻĒā§āϰāĻā§āĻļāϞ⧠āĻšāĻŋāϏā§āĻŦā§ āĻ
āĻŦāĻļā§āϝāĻ āĻāĻĒāύāĻžāϰ āϧāĻžāϰāύāĻž āĻĨāĻžāĻāϤ⧠āĻšāĻŦā§ āĻāĻāĻāĻŋ āĻŦāĻŋāϞā§āĻĄāĻŋāĻā§ā§āϰ āĻŽā§āĻ ā§§ā§Ļā§Ļ% āĻāĻžāĻ āĻāĻŋāĻāĻžāĻŦā§ āĻšāĻŋāϏā§āĻŦ āĻāϰāĻž āĻšā§ā§ āĻĨāĻžāĻā§āĨ¤ āĻāϏā§āύ āĻā§āĻŦ āϏāĻšāĻā§ āĻŽāύ⧠āϰāĻžāĻāĻŋ āĻāĻāĻāĻŋ āĻŦāĻŋāϞā§āĻĄāĻŋāĻ āĻāϰ āϏāĻāϞ āĻāĻāĻā§āĻŽ āĻŽāĻŋāϞ⧠⧧ā§Ļā§Ļ% āĻāĻŋāĻāĻžāĻŦā§ āĻāĻžāĻ āĻāϰāĻž āĻšā§āĨ¤
āϤāĻžāϰ āϏāĻŽā§āĻāĻžāĻŦā§āϝ āύāĻŽā§āύāĻžāĨ¤
1. Structure = 35%
2. Brick work = 6%
3. Wood work = 5%
4. Metal work = 2%
5. Plambing and Sanitary = 6%
6. Electrical work = 7%
7. Plaster work = 4%
8. General Floor Tiles work = 6%
9. Toilet & Kit wall Tiles work = 3%
10. Aluminium work = 4%
11. EME (Lift, Generator, Substation) = 10%
12. Paint work = 3%
13. Others civil work = 6%
14. Utility connection & Bill = 3%
Total = 100%
STRUCTURE 35%
- Footing & Column Padestal = 20%
- Grade Beam, UGWR top Slab = 5%
- GF Column, Stair etc = 4%
- 1st Floor Slab = 9%
- Typical Floor Column (5x3%) = 15%
- 2nd floor slab to roof slab (5x8) = 40%
- Roof top = 7%
TOTAL = 100% (ā§Šā§Ģ% āϝā§āĻāĻžāĻŦā§ āĻāϏāĻŦā§āĨ¤)
BRICK WORK 6%
- GF Brick work = 6%
- 1st floor Brick work = 18%
- 2nd floor Brick work = 18%
- 3rd floor Brick work = 18%
- 4th floor Brick work = 18%
- 5th floor Brick work = 18%
-Roof Top Brick work = 4%
TOTAL = 100% (ā§Ŧ% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
WOOD WORK 5%
- Door frame = 40%
- Main Door Shutter = 15%
- Partex Door Shutter = 35%
- Cat Door & Accessories = 10%
TOTAL = 100% (ā§Ģ% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
METAL WORK 2%
- Window grill = 55%
- Verandah Railling = 20%
- Stair Railling = 10%
- Main gate, Gen-Sub, safety grill = 15%
TOTAL = 100% (⧍% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
PLAMBING & SANITARY 6%
- uPVC vertical line thru duct = 25%
- GI line work = 30%
- Fixture & Fittings = 40%
- Ground Floor = 5%
TOTAL = 100% (ā§Ŧ% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
ELECTRICAL - 7%
- Conduiting inside slab = 10%
- Conduiting on wall i/c MK box=15%
- Cabling work = 55%
- Switch-Socket = 20%
TOTAL = 100% (ā§% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
PLASTER 4%
- Ceiling plaster = 20%
- Internal wall plaster = 50%
- Outside plaster/facing bricks = 30%
TOTAL = 100% (ā§Ē% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
GENERAL FLOOR TILES 6%
- General floor & Verandah = 75%
- Stair, typical lobby & lift wall = 20%
- GF lift lobby, wall, reception = 5%
TOTAL = 100% (ā§Ŧ% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
TOILET & KIT WALL TILES = 3%
- Bath wall = 60%
- Kitchen wall = 20%
- Bath floor = 9%
- Bath counter top = 4%
- Kitchen floor = 3%
- Kitchen counter top =4%
TOTAL = 100% (ā§Š% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
ALUMINIUM WORK 4%
- Outer framing-window sliding= 40%
- Glass shutter-window sliding = 30%
- Verandah sliding = 20%
- Toilet high window = 5%
- Comnon area = 5%
TOTAL = 100% (ā§Ē% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
EME 10%
- Lift = 50%
- Generator = 25%
- Substation = 20%
- PABX, Fire extinguisher etc = 5%
TOTAL = 100% (ā§§ā§Ļ% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
PAINT WORK = 3%
- Upto putty = 40%
- Internal wall&ceiling 1st coat= 20%
- Internal wall&ceiling 2nd coat= 15%
- Outside paint/ceramic Tites = 25%
TOTAL = 100% (ā§Š% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
OTHERS CIVIL WORK = 6%
- Boundary wall = 30%
- Line terracing/Roof top paver= 15%
- LOGO, Gardening & others = 4%
- GF BBC = 14%
- GF pavement & footpath dev = 10%
- Lintel, F/slab, drop wall, counter slab = 20%
- Cable tray = 1%
- Sanitary duct cover, ceiling etc= 4%
- Reception desk, letter box = 2%
TOTAL = 100% (ā§Ŧ% āϝā§āĻāĻžāĻŦā§ āĻšāĻŦā§āĨ¤)
UTILITY CONNECTION & BILL = 3%
- DESA/DESCO = 35%
- TITAS = 20
- WASA = 15%
- Utility bills = 30%
TOTAL = 100%